We are about to rehydrotest a 6" sch 80 pipeline that has been hydrotested 3years ago but was not in use or cathodically protected,is it practicable to hydrotest the flow line with the exact test pressure?if not is it a code requirement and where can I get this requirement in the code.
Counting on your quick response.
Thanks
Julius
julius
Senior Member
 
Posts: 78
Joined: 23 Apr 2011, 03:24
Area of interest: Metallurgy Engineering

Re: Re-hydrotest of pipeline

Postby 1772 » 03 Jul 2014, 20:37

julius,
Please provide more information such as jurisdiction (country, state, province), process (steam, water, gas, oil)...?

Ultimately the testing requirements (RT, hydrostatic, pneumatic, leak, in-process testing) lies with the Owner.
1772
Senior Member
 
Posts: 109
Joined: 02 Sep 2010, 13:07
Area of interest: Manufacturing Engineering


Return to Project Engineers

Who is online

Users browsing this forum: No registered users and 2 guests

cron